1865Software EngineeringMedium
Which of the following is not a change management process?
AReview impact with stakeholders
BNone of the mentioned
CLog the changes
DEstimate impact on effort and schedule
Correct answer
B. None of the mentioned
Explanation
Explanation: All are required for a change.