1907Software EngineeringMedium
How is WINWIN Spiral Model different from Spiral Model?
AIt defines a set of negotiation activities at the beginning of each pass around the spiral
BIt defines tasks required to construct, test, install, and provide user support
CIt defines tasks required to assess both technical and management risks
DIt defines tasks required to define resources, timelines, and other project related information
Correct answer
A. It defines a set of negotiation activities at the beginning of each pass around the spiral
Explanation
Explanation: Except option “b” all other tasks/activities are present in Spiral Model as well.