1979Software EngineeringMedium
The Process Manager has to keep track of________?
Athe information management support to a programmer using the system
Bboth A and B
Cthe status of each program
Dthe priority of each program
Correct answer
B. both A and B
Explanation
The correct answer is both A and B.