Which of the following is a systematic attempt to specify threats to the project plan?
APerformance risk
BRisk identification
CSupport risk
DRisk projection
Correct answer
D. Risk projection
Explanation
Explanation: By identifying known and predictable risks, the project manager takes a first step toward avoiding them when possible and controlling them when necessary.