Which four framework activities are found in the Extreme Programming(XP)?
Aplanning, analysis, design, coding
Bplanning, design, coding, testing
Cplanning, analysis, coding, testing
Danalysis, design, coding, testing
Correct answer
B. planning, design, coding, testing
Explanation
Explanation: XP involves the mentioned four activities, and in the same in order.