713Software EngineeringMedium
Which of the following does not apply to agility to a software process?
AEliminate the use of project planning and testing
BUses incremental product delivery strategy
CAll of the mentioned
DOnly essential work products are produced
Correct answer
A. Eliminate the use of project planning and testing
Explanation
Explanation: Testing is a major part of each software development process which can’t be avoided