848Software EngineeringMedium
Which of the following states that work expands to fill the time available?
ACASE tools
BExpert judgement
CParkinson’s Law
DPricing to win
Correct answer
C. Parkinson’s Law
Explanation
Explanation: The cost is determined by available resources rather than by objective assessment. If the software has to be delivered in 12 months and 5 people are available, the effort required is estimated to be 60 person-months.