A.on all the activities lying on the critical path
B.only on activities lying on the orginal critical path and having flatter cost slopes
C.on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
D.on all the activities
Explanation: The correct answer is on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope.