A.to decrease it on descending grades and to increase it on ascending grades
B.to increase it on both descending and ascending grades
C.to decrease it on both descending and ascending grades
D.to increase it on descending grades and to decrease it on ascending grades
Explanation: The correct answer is to increase it on both descending and ascending grades.

Submitted by: Academy of Pakistan

Share
A.construction of invert is completed before side walls and roof arch are built
B.construction of invert and side walls is completed before roof arch is built
C.construction of roof arch is completed before side walls and invert are built
D.construction of side walls is completed before invert and roof arch are built
Explanation: The correct answer is construction of roof arch is completed before side walls and invert are built.

Submitted by: Academy of Pakistan

Share
A.the head of the load reaches the section
B.the load position should be such that the section divides it equally on both sides
C.the load position should be such that the section divides the load in the same ratio as it divides the
D.the tail of the load reaches the section
Explanation: The correct answer is the load position should be such that the section divides the load in the same ratio as it divides the.