Crash project duration is obtained by summing the________?
Correct answer
D. crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities
Explanation
The correct answer is crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.