2349Civil EngineeringMedium
The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as________?
Aindependent float
Binterfering float
Ctotal float
Dfree float
Correct answer
A. independent float
Explanation
The correct answer is independent float.