1811Civil EngineeringMedium
Earliest finish of an activity is always________?
Aless than or equal to earliest event time of the following node
Bgreater than earliest event time of the following node
Cgreater than or equal to earliest event time of the following node
Dless than earliest event time of the following node
Correct answer
A. less than or equal to earliest event time of the following node
Explanation
The correct answer is less than or equal to earliest event time of the following node.