1816Civil EngineeringMedium
As per IS specifications, the maximum final setting time for ordinary Portland cement should be________?
A6 hours
B30 minutes
C10 hours
D1 hour
Correct answer
C. 10 hours
Explanation
The correct answer is 10 hours.
Correct answer
C. 10 hours
Explanation
The correct answer is 10 hours.