3001Civil EngineeringMedium
The initial setting time for ordinary Portland cement as per IS specifications should not be less than________?
A600 minutes
B60 minutes
C10 minutes
D30 minutes
Correct answer
D. 30 minutes
Explanation
The correct answer is 30 minutes.