1863Mechanical EngineeringMedium
Slack of various events on the critical path in PERT/CPM chart________?
Adecreases continuously
Bmay increase or decrease depending on various factors
Cunpredictable
Dincreases continuously
Eremains constant
Correct answer
E. remains constant
Explanation
The correct answer is remains constant.