1866Mechanical EngineeringMedium
The assumption in PERT is________?
Aa project can be subdivided into a set of predictable, independent activities
Ba project will always be behind schedule, if left uncorrected
Ccommissioning time can be changed, if activities are behind schedule
Dactivities are fixed and can’t be changed,
Ecost of project will always be more than the estimated cost, if no timely corrections are taken
Correct answer
A. a project can be subdivided into a set of predictable, independent activities
Explanation
The correct answer is a project can be subdivided into a set of predictable, independent activities.