1867Mechanical EngineeringMedium
CPM has following time estimate________
Athree time estimate
Bnil time estimate
Ctwo time estimate
Dfour time estimate
Eone time estimate
Correct answer
E. one time estimate
Explanation
The correct answer is one time estimate.